CASE STUDY - Blackrod Interchange
Client Address (area): Bolton
This is one large unit which has up to five different units inside. These vary from catering businesses to logistic companies.
Prior to painting we degreased all the liner panels to remove all grease and oil. We taped up all skylights, light fittings and sprinkler system. We then airless sprayed two coats of Johnstones stain away to achieve the finish required. We filled and fully prepared all breezeblock walls prior to spray applying two coats of Johnstones pliolite masonry paint. Before painting the steel we removed all the tape from the fittings skylights then fully prepared the surface of the steel with mechanical grinders before applying two coats of self priming Johnstones smooth metal paint.
Length of job: 4 weeks (including weekends)
No. of operatives: 6
Access equipment: Diesel Cherry-picker, 2 x Diesel Scissor lifts
Specialist Products: Johnstones stain away, Johnstones smooth metal, Johnstones pliolite masonry paint